Bellaire Avenue Improvements

Project Update  
  
Valley Paving was awarded the contract and work has begun. The city of North St Paul is handling the project, contractor and scheduling of the work.

Work on Bellaire Avenue is currently anticipated to start in July. 

Additional information can be found on the NSP website.
    
 
  

Project Contacts (North St Paul)



Tom Russell         (612) 201-5213
First Contact/Construction Observer

Brad Reifsteck      (763) 512-5243
Project Manager
PROJECT BACKGROUND INFORMATION:

On September 14, 2015, the Maplewood City Council accepted the feasibility study for the Bellaire Avenue Improvements, City Project 15-16, authorized the preparation of plans and specification, and ordered a public hearing. 

The section of Bellaire Avenue (aka Helen St) between Beam Avenue and Lydia Avenue is a border street with the City of North St. Paul (NSP). NSP is leading a large neighborhood reconstruction project in 2016 of which this section of Bellaire is included for pavement rehabilitation and spot curb repair.  Maplewood, in anticipation of this joint project, planned for this work in the currently adopted 2016-2020 Capital Improvement Plan.