Pond-Dorland Area Street Improvements

An informational mailing has been sent out to homeowners in the Pond-Dorland Area regarding the upcoming street improvements.   This information includes general information regarding full street reconstruction and pavement rehabilitation and assessments.

Informational Meeting

Thursday, October 27, 2016 from 6:00pm - 7:30pm
in Room D of the Maplewood Community Center.

Proposed Timeline

Target Dates
Oct 13, 2016
Informational Packet Mailed
Oct 27, 2016
Neighborhood Meeting at 6:00pm - 7:30pm in Room D of the Maplewood Community Center
Nov 28, 2016
Council requested to Accept Feasibility Report, Call for Public Hearing, and Authorize Preparation of Plans and Specifications
Dec 12, 2016 week
Potential Neighborhood Meeting
Dec 12, 2016
Public Hearing and Order Improvement
Jan 9, 2017 week
Potential Neighborhood Meeting
Jan 23, 2017
Council requested to Approve Plans, Authorize Ad for Bid, and Authorize Preparation of Assessment Roll
Feb 13, 2017
Council requested to Accept Assessment Roll and Order Assessment Hearing
Mar 2, 2017
Bid Opening
Mar 13, 2017
Council to hold Assessment Hearing and Award of Contract
April 10, 2017
Council requested to Adopt Revised Assessment Roll
May 8, 2017
Begin construction
  1. Jon Jarosch

    Civil Engineer II
    Phone: (651) 249-2405

Pond/Dorland Map

Location Map Pond Dorland

Streets impacted:

Boxwood Avenue, Dorland Road, Heights Avenue, Overlook Circle, Pond Avenue