Additions

Overview
Additions, either to a dwelling or a garage, require a building permit. Construction plans should include a cross-section of the house, a floor plan, footing plans and a certificate of survey. See the addition/garage handout (PDF) for some code issues. Also, see the single-family lot guidelines (PDF) for standard setbacks from your property lines.

Note: You will be required to have smoke detectors (PDF) in all bedrooms throughout the house at the final inspection for final approval.

Involving a Contractor
If a contractor is constructing the addition, the city requires the contractor to be licensed with either the state or the city of Maplewood.

Documentation required when applying for an addition building permit:
  • Building permit application (PDF) - including project valuation
  • 3 copies of construction plans - including cross-section of house, floor plan, list of materials, roof truss layout, floor truss layout, heat loss calcs, energy calcs and footing plan
  • 3 copies of a certificate of survey or site plan (PDF) - showing proposed addition and all distances to property lines and other buildings
  • Separate permits are required for plumbing (PDF), mechanical (PDF), or electrical (PDF) work